Renewable Energy

Generation, sized
to the incentive.

A rooftop array is an engineering problem and a programme problem at the same time, and the second one usually decides the first. Size a system to the roof and you forfeit the rebate. Size it to the rebate ceiling and the same roof pays back in half the time. We model both, in PVsyst and SAM, before anyone commits to a capital number.

16+ MW
Of renewable generation supported, including design and grid integration
50%
Of gross capital cost removed by stacking the IESO rebate with the federal Clean Tech ITC
P90 / P99
Exceedance cases modelled alongside P50, because a lender finances the downside
What this covers

Feasibility
through design.

We are not an installer and we do not sell panels, which means the study can conclude that a roof is not worth it. That happens, and it is a useful answer to have paid for rather than discovered later.

01

Rooftop and carport feasibility

Usable roof area against structure, obstructions and setbacks; array geometry, tilt and azimuth; yield modelled hour by hour in PVsyst and cross-checked in SAM.

02

Incentive and tax structuring

Which programmes the system qualifies for, what the sizing rules actually cap, and how the rebate and the tax credit interact on the same capital cost.

03

Interconnection and utility coordination

Load displacement sizing against the facility's own peak, single-line development, and the conversation with the local distribution company before the design is fixed.

04

Storage and peak shaving

Battery sizing where it earns its place — against demand charges, Global Adjustment exposure or a demand response commitment, modelled as its own case rather than assumed.

The thing that decides the project

Why a 1.1 MW-DC array
is sized for a
1 MW-AC rebate.

IESO Save on Energy pays $860 per kW-AC on commercial solar, and the cap applies to AC nameplate — inverter output — not to DC panel capacity. A 1.1× DC:AC ratio puts the array right at the eligible ceiling. Going larger forfeits the rebate on the incremental capacity and leaves only the tax credit, so the marginal panel earns considerably less than the ones below it.

This is the sort of thing that is obvious once stated and expensive to discover after a system is quoted. It is also why a roof's physical capacity is rarely the right design target.

  • Micro-generation, ≤10 kW-DC — $1,000 per kW-DC
  • Small and medium, >10 kW-AC to 1 MW-AC — $860 per kW-AC, paid upfront
  • Above 1 MW-AC — still eligible, but the incentive is capped at 1 MW-AC and at 50% of total eligible project cost
  • Sizing rule — load displacement only: system size cannot exceed the facility's maximum load

Programme rates and rules as at the 2026 season. Confirm current terms with the IESO before relying on them; the funding explorer tracks the live figures alongside 109 other routes.

Worked example

1 MW-AC on a
regional mall.

Vaughan Mills, managed by JLL: a 1,547,019 ft² enclosed retail centre consuming 26.3 GWh a year. A feasibility study completed in April 2026 sized a 1.1 MW-DC rooftop array specifically to the Save on Energy ceiling so the IESO rebate and the 30% federal Clean Technology ITC could both be claimed.

Feasibility study · April 2026 · not yet constructed

How the incentives halve the capital cost

Line itemWhat it isShare of gross capital cost
Gross CAPEX1.1 MW-DC rooftop PV, fully installed100%
− Save on Energy RetrofitIESO upfront commercial rebate at $860/kW-AC, capped at 1 MW-AC−26%
− Clean Technology ITCFederal refundable tax credit, 30% on the post-rebate cost basis−21%
Net CAPEXWhat the owner actually funds50%
50%
Of gross capital cost removed by stacking both incentives
7.7yr
Simple payback on net capital
11.3%
Fifteen-year IRR, before financing
5%
Of the facility's annual electricity load covered by the array

The array is 2,445 modules at 450 Wp on fixed racking at 10° tilt and 0° azimuth, 5,401 m² of collector, simulated at 1,369 MWh a year in PVsyst 7.2.4 for a 14.2% capacity factor. That covers about 5% of the facility's annual load and avoids 46.6 tCO2 a year on the Ontario grid factor — using between 10 and 20% of the available roof, with no impact on leasable floor area and no land take. The site's 6,993 kW summer peak comfortably accommodates the array under the load-displacement rule.

A feasibility study, not a delivered installation. Figures are modelled projections at study stage and depend on programme terms, final pricing and interconnection outcome. Capital costs, the facility's utility spend and net present values are commercially confidential to the client and are not published — the percentages above carry the point without them. The $860/kW-AC and $1,000/kW-DC figures are published IESO programme rates.

At portfolio scale

Cold storage,
two sites,
six megawatts.

Two Lineage cold storage facilities carrying 360,521 ft² of roof between them. Modelled at 5° tilt across two roof-utilisation cases, because on an industrial roof the constraint is almost never the sun — it is mechanical equipment, access routes and the structural capacity of the deck.

CaseRoof usedDC capacityP50 generationP90P99
83% roof utilisation300,434 ft²5,994 kW7,599 MWh7,076 MWh6,650 MWh
70% roof utilisation, conservative252,365 ft²5,037 kW6,386 MWh5,946 MWh5,588 MWh

P90 and P99 are the exceedance cases — the generation the array beats in nine years out of ten, and in ninety-nine out of a hundred. Probability coefficients from PVsyst: 0.93 and 0.88 against P50. A P50 number is what a developer quotes; a P90 number is what a lender sizes debt against. Publishing only the first is how a project ends up underperforming a business case that was never wrong, only optimistic.

How we work

Six steps,
same as the
audits.

The underlying process does not change between an energy audit and a solar study — site and data gathering, baseline, scenario modelling, comparison, financial synthesis, verified recommendation. Only the tools change: SAM, PVsyst and OpenSolar here where an audit would use RETScreen and eQUEST.

01 · Site & load assessment
Roof survey, structural and obstruction constraints, and twelve months of interval data to establish the facility's own peak and load shape. Load displacement sizing starts here, not from the roof area.
02 · Array geometry
Tilt, azimuth, row spacing and usable area, against realistic utilisation rather than a plan-view maximum.
03 · Yield simulation
Hourly production modelled in PVsyst, cross-checked in SAM, with P50, P90 and P99 cases reported rather than a single number.
04 · Incentive structuring
Sizing tuned to the programme ceilings, with the interaction between the upfront rebate and the tax credit worked through on the actual cost basis.
05 · Financial synthesis
Net capital, annual savings, payback, IRR and NPV, with the sensitivity that matters stated — usually electricity price and utilisation, not module cost.
06 · Recommendation
Including, where the numbers say so, a recommendation not to proceed. A roof that does not pencil out is a finding.
FAQ

Common questions.

A refundable federal tax credit on capital invested in new clean-technology property in Canada — 30% for property in service between 28 March 2023 and 31 December 2033, dropping to 15% in 2034. Refundable means the benefit arrives even with no tax payable. The full 30% requires electing to meet prevailing-wage and apprenticeship labour requirements; without that election it is 20%. Taxable Canadian corporations and REIT mutual fund trusts can claim it; sole proprietors cannot. Confirm treatment with your own tax advisor — we model it, we do not opine on it.

Yes, and that stacking is usually what makes a commercial rooftop project work. The ITC applies to the post-rebate cost basis, not the gross, so the order matters to the arithmetic. What you cannot do is claim two ITCs on the same equipment — the Clean Tech ITC and the Carbon Capture ITC are mutually exclusive per property, though a project with different equipment types can claim across components. It does stack with accelerated capital cost allowance under Classes 43.1 and 43.2.

It depends almost entirely on the electricity price the building pays and on whether the incentives can be stacked, not on irradiance. A 14% capacity factor is unremarkable; a project that halves its capital cost and displaces power at commercial retail rates is not. On the industrial recycling portfolio we studied, simple payback ran fourteen years with the Save on Energy incentive alone and as little as six once the tax credit was stacked on top. Same roof, same sun.

No. We do the feasibility, the design, the incentive structuring and the EPC decision support, then run the procurement and oversee delivery through our project management practice. Not selling the hardware is what lets the study say no.

Next step

Thirty minutes, with the engineer who would run the work.

No cost and no obligation. Bring twelve months of utility bills if you have them — that alone is usually enough to say whether a building has a capital problem or a controls problem.